HESI A2
HESI A2 Math
1. If two workers can finish building a play set in 18 hours, how long will it take 4 workers to build 3 play sets?
- A. 27 hours
- B. 36 hours
- C. 24 hours
- D. 54 hours
Correct answer: A
Rationale: If 2 workers can complete building one play set in 18 hours, it means one worker would take 36 hours to complete the same task. When the number of workers is doubled to 4, the time is halved, so 4 workers would take 18 hours to build one play set. To build 3 play sets, the total time needed would be 3 times the time for one play set, which equals 54 hours. Therefore, 4 workers can build 3 play sets in 27 hours, making choice A the correct answer. Choices B, C, and D are incorrect because they do not account for the correct relationship between the number of workers and the time required to complete the task.
2. A clinic sees an average of 25 patients every 4 hours. If the clinic is open for 8 hours, how many patients will they see in total?
- A. 35
- B. 50
- C. 75
- D. 200
Correct answer: D
Rationale: Rationale: 1. First, determine how many patients the clinic sees in one hour: 25 patients / 4 hours = 6.25 patients per hour (approximately 6 patients per hour) 2. Since the clinic is open for 8 hours, multiply the number of patients seen per hour by the number of hours the clinic is open: 6.25 patients/hour * 8 hours = 50 patients 3. Therefore, the clinic will see a total of 50 patients in 8 hours, which corresponds to answer choice D) 200.
3. How many meters are in 2 kilometers?
- A. 100 meters
- B. 200 meters
- C. 2000 meters
- D. 3000 meters
Correct answer: C
Rationale: 1 kilometer equals 1,000 meters. Therefore, 2 kilometers equals 2,000 meters. Choice A, 100 meters, is incorrect as it represents only 1/10th of a kilometer. Choice B, 200 meters, is incorrect as it represents only 1/5th of a kilometer. Choice D, 3000 meters, is incorrect as it miscalculates the conversion from kilometers to meters.
4. The price of an item increased from $9.00 to $10.00. What percentage did the price increase by?
- A. 5%
- B. 11.11%
- C. 20%
- D. 25%
Correct answer: B
Rationale: To calculate the percentage increase, subtract the original price from the new price, then divide the result by the original price and multiply by 100. In this case, the increase is $10.00 - $9.00 = $1.00. $1.00 divided by $9.00 is approximately 0.1111, which equals 11.11%, making choice B the correct answer. Choice A, 5%, is too low as the increase is more than 5%. Choice C, 20%, and choice D, 25%, are too high, exaggerating the actual increase of $1.00.
5. In a bar graph showing the number of patients admitted to the ER each day for a week, how do you determine the day with the highest number of admissions?
- A. Find the tallest bar in the graph.
- B. Compare the heights of all bars.
- C. Calculate the average number of admissions per day.
- D. Subtract the lowest number of admissions from the highest.
Correct answer: A
Rationale: The correct answer is A: 'Find the tallest bar in the graph.' In a bar graph, the height of each bar represents the quantity being measured. The tallest bar indicates the day with the highest number of admissions. Therefore, this is the most direct and accurate method to determine the day with the highest number of admissions. Choices B, C, and D are incorrect because comparing all bars, calculating the average, or subtracting the lowest from the highest does not directly identify the day with the highest number of admissions in a bar graph.
Similar Questions
Access More Features
HESI A2 Basic
$49/ 30 days
- 3,000 Questions with answers
- 30 days access
HESI A2 Premium
$99/ 90 days
- Actual HESI A2 Questions
- 3,000 questions with answers
- 90 days access