two workers can finish building a play set in 18 hours how long will it take 4 workers to build 3 play sets
Logo

Nursing Elites

HESI A2

HESI A2 Math

1. If two workers can finish building a play set in 18 hours, how long will it take 4 workers to build 3 play sets?

Correct answer: A

Rationale: If 2 workers can complete building one play set in 18 hours, it means one worker would take 36 hours to complete the same task. When the number of workers is doubled to 4, the time is halved, so 4 workers would take 18 hours to build one play set. To build 3 play sets, the total time needed would be 3 times the time for one play set, which equals 54 hours. Therefore, 4 workers can build 3 play sets in 27 hours, making choice A the correct answer. Choices B, C, and D are incorrect because they do not account for the correct relationship between the number of workers and the time required to complete the task.

2. How many centimeters are in 1 foot?

Correct answer: A

Rationale: The correct answer is A, which is 30.48. To convert inches to feet, since there are 12 inches in a foot, you need to multiply the conversion factor from inches to centimeters (2.54 cm) by the number of inches in a foot (12). This gives 30.48 cm in 1 foot. Choice B, 35, is incorrect as it does not follow the correct conversion. Choices C and D, 25 and 40 respectively, are also incorrect conversions and do not align with the conversion factors provided in the question.

3. Convert this military time to regular time: 0705 hours.

Correct answer: A

Rationale: In military time, 0705 hours translates to 7:05 A.M. Military time follows a 24-hour clock format, so there is no change from A.M. to P.M. like in regular time. Choice B (7:05 P.M.) is incorrect as 0705 hours is in the morning. Choices C (5:07 A.M.) and D (5:07 P.M.) are incorrect due to the incorrect order of hours and minutes.

4. A lab needs 200ml of a 5% salt solution. They only have a 10% solution. How much 10% solution and water should be mixed?

Correct answer: B

Rationale: Rationale: 1. Let x be the volume of the 10% solution needed and y be the volume of water needed. 2. The total volume of the final solution is 200ml, so x + y = 200. 3. The concentration of the final solution is 5%, so the amount of salt in the final solution is 0.05 * 200 = 10g. 4. The amount of salt in the 10% solution is 0.1x, and the amount of salt in the water is 0, so the total amount of salt in the final solution is 0.1x. 5. Since the total amount of salt in the final solution is 10g, we have 0.1x = 10. 6. Solving for x, we get x = 100ml. 7. Substituting x =

5. Which numeric system was a base 20 system?

Correct answer: A

Rationale: The Mayan numeric system was a base 20 system, known as vigesimal, as it used base 20 numerals. This system was unique and employed a combination of symbols and positional notation to represent numbers. The Babylonian system was a base 60 system, Roman numerals were based on combinations of letters, and Arabic numerals are in base 10, making choices B, C, and D incorrect.

Similar Questions

Jeff needed a 6 ft. rope. He found 2 pieces of rope and thought maybe he could tie them together. One rope was 40 inches and the other was 36 inches. How long would the rope be, and would he have enough rope if he ties them together?
There are 225 pieces of candy in a large jar. Ben wants to give the 25 campers in his group an equal amount of candy. How many pieces of candy will each camper receive?
Which of the following percentages is equal to 0.45?
The metric system of measurement was developed in France during Napoleon's reign. It is based on what multiplication factor?
What is 70% of 200?

Access More Features

HESI A2 Basic
$49/ 30 days

  • 3,000 Questions with answers
  • 30 days access

HESI A2 Premium
$99/ 90 days

  • Actual HESI A2 Questions
  • 3,000 questions with answers
  • 90 days access

Other Courses