HESI A2
HESI A2 Math Practice Test
1. What is the result of multiplying 8 by 2?
- A. 16
- B. 22
- C. 24
- D. 32
Correct answer: A
Rationale: The correct answer is A: 16. When you multiply 8 by 2, the result is 16. Choice B (22), Choice C (24), and Choice D (32) are incorrect as they do not represent the correct multiplication of 8 by 2.
2. How many inches are in 2 yards?
- A. 36 inches
- B. 48 inches
- C. 60 inches
- D. 72 inches
Correct answer: D
Rationale: To convert yards to inches, remember that there are 36 inches in a yard. Therefore, when you have 2 yards, multiplying 36 inches by 2 results in 72 inches. Choice A, 36 inches, is the number of inches in 1 yard, not 2 yards. Choice B, 48 inches, and Choice C, 60 inches, are incorrect calculations based on the conversion factor of 36 inches per yard.
3. How many kilograms are equivalent to 20 pounds?
- A. 9 kilograms
- B. 16 kilograms
- C. 44 kilograms
- D. 3 kilograms
Correct answer: A
Rationale: To convert pounds to kilograms, you need to multiply the number of pounds by 0.4536. Therefore, to find out how many kilograms are in 20 pounds, you would calculate 20 x 0.4536 = 9.072 kilograms, which is approximately 9 kilograms. Choice A is correct. Choice B (16 kilograms), Choice C (44 kilograms), and Choice D (3 kilograms) are all incorrect conversions of pounds to kilograms.
4. A die is rolled. What is the probability of getting 5?
- A. 16.67%
- B. 20%
- C. 50%
- D. 83.33%
Correct answer: A
Rationale: The correct answer is A: 16.67%. When rolling a standard 6-sided die, each face has an equal probability of 1/6. Therefore, the probability of rolling a 5 specifically is 1/6, which is approximately 16.67% when converted to a percentage. Choices B, C, and D are incorrect because they do not reflect the correct probability of rolling a 5 on a standard die.
5. A team from the highway department can replace 14 streetlights in 7 hours of work. If they work a 30-hour week at this job, in how many weeks will they replace all 120 downtown streetlights?
- A. 1½ weeks
- B. 2 weeks
- C. 2½ weeks
- D. 3 weeks
Correct answer: B
Rationale: If the team can replace 14 streetlights in 7 hours, it means they replace 2 streetlights per hour. In a 30-hour week, they can therefore replace 2 x 30 = 60 streetlights. To replace all 120 downtown streetlights, they will need 120 / 2 = 60 hours, which is equivalent to 60 / 30 = 2 weeks. Therefore, the correct answer is 2 weeks. Choice A, 1½ weeks, is incorrect because it doesn't consider the total number of streetlights that need to be replaced. Choice C, 2½ weeks, is incorrect as it overestimates the time needed. Choice D, 3 weeks, is incorrect as it underestimates the efficiency of the team in replacing streetlights.
Similar Questions
Access More Features
HESI A2 Basic
$49/ 30 days
- 3,000 Questions with answers
- 30 days access
HESI A2 Premium
$99/ 90 days
- Actual HESI A2 Questions
- 3,000 questions with answers
- 90 days access