a car travels 240 miles in 4 hours what is its speed in miles per hour
Logo

Nursing Elites

HESI A2

HESI A2 Math Practice Test 2023

1. A car travels 240 miles in 4 hours. What is its speed in miles per hour?

Correct answer: B

Rationale: To calculate speed, divide the distance traveled by the time taken: 240 miles ÷ 4 hours = 60 mph. Therefore, the correct answer is B. Choice A (50 mph) is incorrect as it results from an incorrect calculation. Choice C (55 mph) and D (75 mph) are also incorrect because they are not the correct result of dividing 240 miles by 4 hours.

2. A gross is equal to 12 dozen. If Lanyard Farms sells 15 gross of eggs a week and packages them in one dozen egg containers, how many containers do they need for a week’s worth of eggs?

Correct answer: C

Rationale: Given that a gross is equal to 12 dozen, 15 gross of eggs would be equal to 15 * 12 = 180 dozen eggs. Since the eggs are packaged in one dozen egg containers, Lanyard Farms would need 180 containers for a week's worth of eggs. Choice A (15) is incorrect as it represents the number of gross, not containers. Choice B (150) is incorrect as it miscalculates the total number of containers needed. Choice D (2,160) is incorrect as it overestimates the number of containers required.

3. Which of the following numbers is the largest? (0.667, 0.68, 0.6, 0.0688)

Correct answer: B

Rationale: To determine the largest number among the given decimals, compare them. 0.68 is the largest number as it is greater than 0.667, 0.6, and 0.0688. The correct answer is 0.68 because it has the highest value. The other options are smaller: 0.667 is less than 0.68, 0.6 is less than 0.68, and 0.0688 is significantly smaller than 0.68.

4. If two workers can finish building a play set in 18 hours, how long will it take 4 workers to build 3 play sets?

Correct answer: A

Rationale: If 2 workers can complete building one play set in 18 hours, it means one worker would take 36 hours to complete the same task. When the number of workers is doubled to 4, the time is halved, so 4 workers would take 18 hours to build one play set. To build 3 play sets, the total time needed would be 3 times the time for one play set, which equals 54 hours. Therefore, 4 workers can build 3 play sets in 27 hours, making choice A the correct answer. Choices B, C, and D are incorrect because they do not account for the correct relationship between the number of workers and the time required to complete the task.

5. Solve: 8x = x^2.

Correct answer: C

Rationale: To solve the equation 8x = x^2, rearrange it to x^2 - 8x = 0. Factor out an x to get x(x - 8) = 0. Set each factor to zero to find the solutions: x = 0 or x = 8. Therefore, x = 16 is the correct answer because x = 0 is not in the answer choices, and x = 8 is a distraction meant to confuse. Thus, choice C, 16, is the correct solution to the equation.

Similar Questions

What is the result of the expression 4/5 + 6/7?
How many milliliters are in 6 liters?
The head nurse at the hospital has a team of six nurses and one phlebotomist. If the phlebotomist is responsible for 1/7 of the patients, what fraction of the patients is each nurse responsible for?
What is the probability of rolling an odd number on a six-sided die?
You need 4/5 cups of water for a recipe. You accidentally put 1/3 cups into the mixing bowl with the dry ingredients. How much more water in cups do you need to add?

Access More Features

HESI A2 Basic
$49/ 30 days

  • 3,000 Questions with answers
  • 30 days access

HESI A2 Premium
$99/ 90 days

  • Actual HESI A2 Questions
  • 3,000 questions with answers
  • 90 days access

Other Courses