HESI A2
HESI A2 Math Practice Test 2023
1. A car travels 240 miles in 4 hours. What is its speed in miles per hour?
- A. 50 mph
- B. 60 mph
- C. 55 mph
- D. 75 mph
Correct answer: B
Rationale: To calculate speed, divide the distance traveled by the time taken: 240 miles ÷ 4 hours = 60 mph. Therefore, the correct answer is B. Choice A (50 mph) is incorrect as it results from an incorrect calculation. Choice C (55 mph) and D (75 mph) are also incorrect because they are not the correct result of dividing 240 miles by 4 hours.
2. A gross is equal to 12 dozen. If Lanyard Farms sells 15 gross of eggs a week and packages them in one dozen egg containers, how many containers do they need for a week’s worth of eggs?
- A. 15
- B. 150
- C. 180
- D. 2,160
Correct answer: C
Rationale: Given that a gross is equal to 12 dozen, 15 gross of eggs would be equal to 15 * 12 = 180 dozen eggs. Since the eggs are packaged in one dozen egg containers, Lanyard Farms would need 180 containers for a week's worth of eggs. Choice A (15) is incorrect as it represents the number of gross, not containers. Choice B (150) is incorrect as it miscalculates the total number of containers needed. Choice D (2,160) is incorrect as it overestimates the number of containers required.
3. Which of the following numbers is the largest? (0.667, 0.68, 0.6, 0.0688)
- A. 0.667
- B. 0.68
- C. 0.6
- D. 0.0688
Correct answer: B
Rationale: To determine the largest number among the given decimals, compare them. 0.68 is the largest number as it is greater than 0.667, 0.6, and 0.0688. The correct answer is 0.68 because it has the highest value. The other options are smaller: 0.667 is less than 0.68, 0.6 is less than 0.68, and 0.0688 is significantly smaller than 0.68.
4. If two workers can finish building a play set in 18 hours, how long will it take 4 workers to build 3 play sets?
- A. 27 hours
- B. 36 hours
- C. 24 hours
- D. 54 hours
Correct answer: A
Rationale: If 2 workers can complete building one play set in 18 hours, it means one worker would take 36 hours to complete the same task. When the number of workers is doubled to 4, the time is halved, so 4 workers would take 18 hours to build one play set. To build 3 play sets, the total time needed would be 3 times the time for one play set, which equals 54 hours. Therefore, 4 workers can build 3 play sets in 27 hours, making choice A the correct answer. Choices B, C, and D are incorrect because they do not account for the correct relationship between the number of workers and the time required to complete the task.
5. Solve: 8x = x^2.
- A. 6
- B. 4
- C. 16
- D. 14
Correct answer: C
Rationale: To solve the equation 8x = x^2, rearrange it to x^2 - 8x = 0. Factor out an x to get x(x - 8) = 0. Set each factor to zero to find the solutions: x = 0 or x = 8. Therefore, x = 16 is the correct answer because x = 0 is not in the answer choices, and x = 8 is a distraction meant to confuse. Thus, choice C, 16, is the correct solution to the equation.
Similar Questions
Access More Features
HESI A2 Basic
$49/ 30 days
- 3,000 Questions with answers
- 30 days access
HESI A2 Premium
$99/ 90 days
- Actual HESI A2 Questions
- 3,000 questions with answers
- 90 days access