HESI A2
HESI A2 Math Practice Test 2024
1. Bill has 2.5 vacation days left for the rest of the year and 1.25 sick days left. If Bill uses all of his sick days and his vacation days, how many days will he have off work?
- A. 1 day
- B. 3 days
- C. 2 days
- D. 4 days
Correct answer: D
Rationale: To find the total number of days Bill will have off, add his vacation days and sick days together. Bill has 2.5 vacation days and 1.25 sick days: 2.5 + 1.25 = 3.75 days When rounding to the nearest whole number, 3.75 rounds up to 4. Therefore, Bill will have 4 days off work.
2. A plan for a shed is drawn on a 1:10 scale. If the roof of the real shed measures 4 feet by 5 feet, what were the measurements on the plan?
- A. 80 inches by 100 inches
- B. 40 inches by 50 inches
- C. 4.8 inches by 6 inches
- D. 4 inches by 5 inches
Correct answer: B
Rationale: When the real shed roof measures 4 feet by 5 feet, on a 1:10 scale plan, the measurements on the plan would be 1/10 of the real measurements. Therefore, the correct answer is 40 inches by 50 inches since it represents 1/10 of 4 feet by 5 feet. Choice A (80 inches by 100 inches) is incorrect because it is equivalent to the real shed measurements, not the scaled plan. Choice C (4.8 inches by 6 inches) is incorrect as it does not reflect the 1:10 scale reduction. Choice D (4 inches by 5 inches) is incorrect because it does not consider the scale factor of 1:10.
3. If two workers can finish building a play set in 18 hours, how long will it take 4 workers to build 3 play sets?
- A. 27 hours
- B. 36 hours
- C. 24 hours
- D. 54 hours
Correct answer: A
Rationale: If 2 workers can complete building one play set in 18 hours, it means one worker would take 36 hours to complete the same task. When the number of workers is doubled to 4, the time is halved, so 4 workers would take 18 hours to build one play set. To build 3 play sets, the total time needed would be 3 times the time for one play set, which equals 54 hours. Therefore, 4 workers can build 3 play sets in 27 hours, making choice A the correct answer. Choices B, C, and D are incorrect because they do not account for the correct relationship between the number of workers and the time required to complete the task.
4. If a dice is rolled, what is the probability of getting an even number?
- A. 16%
- B. 33%
- C. 66%
- D. 50%
Correct answer: D
Rationale: When rolling a standard six-sided die, there are three even numbers (2, 4, 6) out of a total of six possible outcomes (1, 2, 3, 4, 5, 6). The probability of rolling an even number can be calculated as the number of favorable outcomes (3) divided by the total number of outcomes (6), which equals 3/6 = 50%. Therefore, the correct answer is D. Choice A (16%) is incorrect because it does not represent the probability of rolling an even number. Choice B (33%) is incorrect as it does not reflect the correct probability. Choice C (66%) is incorrect as well since it overestimates the probability.
5. What is 0.9 divided by 3?
- A. 0
- B. 3
- C. 0.3
- D. 9
Correct answer: C
Rationale: To find the result of dividing 0.9 by 3, we perform the division operation, which equals 0.3. Therefore, the correct answer is 0.3. Choice A (0) is incorrect as the result is not zero, but 0.3. Choice B (3) is incorrect as 0.9 divided by 3 is not 3 but 0.3. Choice D (9) is incorrect as 0.9 divided by 3 is not 9 but 0.3.
Similar Questions
Access More Features
HESI A2 Basic
$99/ 30 days
- 3,000 Questions with answers
- 30 days access
HESI A2 Premium
$149.99/ 90 days
- Actual HESI A2 Questions
- 3,000 questions with answers
- 90 days access